Ministry of Oil Building |
|
|
Name of
Project : Admin. Building for Ministry of Oil and
Mineral
Location: Al Zubairy Street
- Sana’a (R of Yemen).
Description:
-
COVERED AREA= 15,000 M2.
-
STONE MASONRY = 20,000 M2
-
CONCRETING~ 16,000 M2.
-
ALUMINUM WORK FOR WiNDOW AND
ELE\’ATION GLASS~ 5,000 M
-
MARBLE WORK 5000 M2.
-
GERAINT WORK 3000 M2
-
LIFTS 6 NOS. GENERATOR AND
ELECTROMECHANIC WORK.
-
ADMINISTRATION DEPTT.
-
MINISTERS OFFICE.
-
VICE AND DEPUTY MINISTERS
OFFICE.
-
LANDSCAPING.
-
EXTERNAL FENCING
-
CONC. PAVEMENT.
-
GENERATOR AND TRANSFORMER 1500
KVA.
-
MAIN DISTRIBUTION BOARD AND
OVER HEAD LiNE.
-
FIRE ALARM AND FIRE FIGHTING
SYSTEM
-
LIGHTING AND EARTHING SYSTEM.
|
 |
|
 |
|
Post Office |
|
|
PROJECT TITLE |
Central Post Office . |
|
LOCATION |
Sana'a, Rep. of Yemen |
|
CLIENT |
Ministry of Communication . |
|
CONSULTANT |
Hafiz & Mirjan Egypt - Ministry of
Construction |
|
FORM OF CONTRACT |
Main Contarct |
|
CONTRACT PERIOD |
1991 - 1993. |
|
CONTRACT AMOUNT |
US $ 9,000,000. |
|
SOURCE OF FUND |
Local |
PROJECT DETAILS
- AREA COVERED 12,000 M² .
- ADMINISTRATION BUILDING FOR TELECOMMUNICATION.
- CONSISTS OF ADMINISTRATIVE AND POSTAL CLEARANCE DEPTT.
- MEETING HALL.
- GENERATOR ROOM.
- LANDSCAPING
- ASPHALTING.
- FOUNTAINS AND GREENERY.
- REINFORCED CONCRETING FOR STRUCTURES 12,000 M³ .
- DRESSED STONE MASONRY 9,000 M²
|
 |
|
 |
|
Custom Building |
|
Location: Sana'a
Date: 1997
Costs: Y.R. 95 Million |
 |
|
Correctional House |
Juvenile Home |
Location: Ibb
Date: 82 - 1983
Costs: Y.R. 11 Million |
Location: Taiz
Date: 1979
Costs: Y.R. 8 Million |
|
Tax Office |
Location: Sana'a
Date: 80 - 1982
Costs: Y.R. 5 Million |
 |
|
Radio Transmission Building
|
Social Correctional Centre
|
Location: Sana'a
Date: 79 - 1981
Costs: Y.R. 7 Million |
Location: Ibb
Date: 82 - 1983
Costs: Y.R. 24 Million |
|
|